Construction of high-pressure gas pipeline from Bytów to Słupsk

client: Polska Spółka Gazownictwa Sp. z o.o. Oddział w Gdańsku
Completion date: 10.09.2007 – 17.12.2008

Construction of high-pressure gas pipeline DN 300/250 6.3 MPa from Bytów to Słupsk with the following scope:

  • DN 300 gas pipeline with length of 62,827 linear meters.
  • DN 250 gas pipeline with length of 15,603 linear meters.
  • First stage reduction and metering station Q = 20,000 m3/h in Redzikowo.
  • DN 300 pig launcher in Mądrzechowo.
  • DN 250 pig launcher in Widzino.
  • DN 300 pig receiver in Reblino - inline block valve stations in Borzytuchom and Suchora locations.

LATEST PROJECTS

Budowa Gazociągu Racibórz-Oświęcim
CONSTRUCTION OF GAS PIPELINE DN700 FROM RACIBÓRZ TO OŚWIĘCIM
Construction of a 38.6 km high-pressure gas pipeline with MOP 8.4 MPa, diameter 700mm along with technological facilities...
CONSTRUCTION OF BOROWO-5, GRANÓWKO-1 AND SZCZEPOWICE-1
Construction of high-pressure gas pipelines along with formation water pipelines as part of the development...
Construction of DN300/250 gas pipeline from SN Kłodawa to SN...
Construction of a 42 km high-pressure gas pipeline with MOP 6.3 MPa, diameter 250/300mm along with technological facilities...
Budowa Gazociągu Racibórz-Oświęcim
CONSTRUCTION OF GAS PIPELINE DN700 FROM RACIBÓRZ TO OŚWIĘCIM
Construction of a 38.6 km high-pressure gas pipeline with MOP 8.4 MPa, diameter 700mm along with technological facilities...
CONSTRUCTION OF BOROWO-5, GRANÓWKO-1 AND SZCZEPOWICE-1
Construction of high-pressure gas pipelines along with formation water pipelines as part of the development...
CONSTRUCTION OF GAS PIPELINE DN300/250 FROM SN KŁODAWA TO SN WITNICA
Construction of a 42 km high-pressure gas pipeline with MOP 6.3 MPa, diameter 250/300mm along with technological facilities...