CONSTRUCTION OF BOROWO-5, GRANÓWKO-1 AND SZCZEPOWICE-1

client: PKN ORLEN S.A.
Completion date: 02.2023 - 06.2024

Project name:

Comprehensive construction and assembly works related to construction of gas pipelines, pipelines and cable ducts with infrastructure and connection, including formal and legal matters; implemented as part of the Investment "Development of Borowo-5, Granówko-1 and Szczepowice-1 wells"

General Contractor: PGNiG Technologie S.A

Scope of work:

Construction of high-pressure gas pipelines with formation water pipelines as part of development of wellhead zones Borowo, Granówko, Szczepowice with total length of approx. 60 km including associated telecommunications infrastructure.

LATEST PROJECTS

Budowa Gazociągu Racibórz-Oświęcim
CONSTRUCTION OF GAS PIPELINE DN700 FROM RACIBÓRZ TO OŚWIĘCIM
Construction of a 38.6 km high-pressure gas pipeline with MOP 8.4 MPa, diameter 700mm along with technological facilities...
CONSTRUCTION OF BOROWO-5, GRANÓWKO-1 AND SZCZEPOWICE-1
Construction of high-pressure gas pipelines along with formation water pipelines as part of the development...
Construction of DN300/250 gas pipeline from SN Kłodawa to SN...
Construction of a 42 km high-pressure gas pipeline with MOP 6.3 MPa, diameter 250/300mm along with technological facilities...
Budowa Gazociągu Racibórz-Oświęcim
CONSTRUCTION OF GAS PIPELINE DN700 FROM RACIBÓRZ TO OŚWIĘCIM
Construction of a 38.6 km high-pressure gas pipeline with MOP 8.4 MPa, diameter 700mm along with technological facilities...
CONSTRUCTION OF BOROWO-5, GRANÓWKO-1 AND SZCZEPOWICE-1
Construction of high-pressure gas pipelines along with formation water pipelines as part of the development...
CONSTRUCTION OF GAS PIPELINE DN300/250 FROM SN KŁODAWA TO SN WITNICA
Construction of a 42 km high-pressure gas pipeline with MOP 6.3 MPa, diameter 250/300mm along with technological facilities...