Project name:
Construction of water main and network in Kórnik
General Contractor: Consortium of companies: TERLAN Sp. z o.o. (Consortium Leader) and WUPRINŻ S.A. (Consortium Partner)
Scope of work:
- Preparatory works.
- Comprehensive construction of water network with total length of approx. 15,666.8m, including:
- Construction of water main DN 500 with length of approx. 12,954.80 m (stage Ia) on section from eastern main to border of Mosina and Kórnik municipalities in Mieczewo including vegetation removal and surface restoration
- Construction of water main DN 400 with length of approx. 2,712.00 m (stage Ib) along provincial road No. 431 and 434, from border of Mosina and Kórnik municipalities in Mieczewo to Mościennicka Street in Kórnik including vegetation removal and surface restoration
- Execution of 47 trenchless crossings under existing infrastructure i.e. directional drilling with GRP DN600 and DN750 casing pipes.
- Pressure testing.